advertisement
Video Editor: Deepthi Ramdas
We are a group of homebuyers who had purchased flats by VP Spaces builders in Bhiwadi in 2014.
Most of us paid 95 percent of the payment upfront and were supposed to get a 12 percent return on the amount until the builder gave us possession of the flat. However, at the time of signing the contract, ‘till possession’ became ‘till offer of possession’.
When we raised this point we were told that we need not worry as the offer of possession is made just before the actual possession.
Trouble began in October 2017, when our return was stopped. Soon after in January 2018, the offer of possession was rolled out with the demand for the pending amount.
In that payment, additional charges were added like the ‘sinking fund’ etc which
weren’t disclosed to us before we made all those payments in May 2018.
After making payments we inspected the site and were shocked to learn the flats were nowhere near completion. Delivery was promised in December 2018.
When we raised this with the builder, we were given false assurance that the flat would be completed soon. Come November 2019, we don't have any clarity on the return we were supposed to get or on the delivery of the flat.
Upon some investigation at a personal level, we found that the builder hasn’t even got the required completion certificate from the authority. An RTI was raised with Bhiwadi Integrated Development Authority (BIDA) which provided us the information. A completion certificate is a minimum requirement for rolling out the offer of possession.
We were promised other facilities like society club, lawns, badminton courts, etc. But there is nothing near completion as of now. In fact, what has been constructed is falling apart. The flat is already damaged due to poor construction. The plaster was crumbling the last time I went there. Bhumit, a fellow homebuyer, feels the same.
A question that arises is how an offer of possession was rolled out in January 2018 without the completion certificate. Secondly, despite it being mentioned in the contract, the builder is not giving us a 12 percent assured return since October 2017, ie 2 years.
As per RERA Rajasthan, the buyer has the right to ask for a complete refund with interest in case the project is not delivered within the agreed time frame. Will the builder agree?
(VP Spaces was unavailable for comment. The story will be updated if there is a response.)
(All 'My Report' branded stories are submitted by citizen journalists to The Quint. Though The Quint inquires into the claims/allegations from all parties before publishing, the report and the views expressed above are the citizen journalist's own. The Quint neither endorses, nor is responsible for the same.)
(At The Quint, we question everything. Play an active role in shaping our journalism by becoming a member today.)
Published: 11 Nov 2019,01:57 PM IST