Worst Year Ever For MGNREGA, 23 Percent Drop In Assets Created

Poor participation shows that work is either not provided or demanded.

IndiaSpend
India
Updated:
Labourers work on a dried lake to try and revive it under the Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA) on the outskirts of Hyderabad. (Photo: Reuters)
i
Labourers work on a dried lake to try and revive it under the Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA) on the outskirts of Hyderabad. (Photo: Reuters)
null

advertisement

After spending about Rs 3.5 lakh crore ($51 billion) – almost equal to India’s subsidy and pensions budget for 2015-16 – over 10 years on the world’s largest rural jobs programme, it has provided less than half the guaranteed 100 days of employment to 50 million poor households.

This is revealed in our analysis of Mahatma Gandhi National Rural Employment Guarantee (MGNREGA) data. Other facts:

  • Although the most money ever was spent during 2015-16, it was the worst year ever in terms of assets created (2.27 million assets), a 23 percent decline from 2014-15.
  • While 50 million households found work through MGNREGA last year, less than 10 percent of these households got 100 days of wage employment.
  • Just about 40 percent of the workers get paid within the promised 15-day period.
  • Women now hold half of all MGNREGA jobs, higher than the mandated 33 percent.

A safety net for rural areas, MGNREGA guarantees 100 days of paid, unskilled manual work every year to every rural household.

“It is the largest and perhaps the most ambitious social security and public works programme in the world,” said Jairam Ramesh, former union rural development minister, who launched MGNREGA.

With the programme completing 10 years, we evaluated its impact. Here’s a look at the national-level data for the past four financial years.

Clearly, the popular demand of increasing the number of guaranteed work days under MGNREGA will not help since the existing promise of 100 days is not being met.

Barely 50 million households have found work through MGNREGA and less than 10 percent of these households have been able to get 100 days of wage employment. Clearly, either work is not being provided or not being demanded.

Just about 40 percent of the workers get paid within the promised 15 days. For unskilled MGNREGA workers, not getting paid in time is detrimental to domestic finances. Perhaps this will change with 210 million new Jan Dhan (People’s Wealth) accounts opened, into which the government can directly pay wages.

ADVERTISEMENT
ADVERTISEMENT

There has been no significant increase in the number of assets created each year, with last year the worst ever, as we said, with a 23 percent drop from 2014-15.

The durability of the assets is questionable. Currently, the law says that 60 percent of funds should be spent on wages and 40 percent on material, which means a preponderance of labour-intensive works, not structures that require more and better material.

MGNREGA has brought parity in labour force participation, one of its few successes.

There has been a constant demand to increase the MGNREGA budget. The most money was spent last year, Rs 42,084 crore, about 0.3 percent of India’s Gross Domestic Product (GDP).

More than 95 percent of MGNREGA funds have been used over the last two years. This is a positive, but there are allegations of corruption.

The expenditure on agriculture was the highest ever in 2015-16.

Per person wage and cost have gone up steadily over the years. The average wage rate in 2015-16 was Rs 154 per day, a 27 percent increase from four years ago. Yet, the labour participation in MGNREGA has not grown, proven by the fact that only 2.3 billion person-days of labour were generated both in 2015-16 and 2012-13, despite a 27 percent wage increase. Critics claim MGNREGA wage rates have distorted the farm labour market while supporters argue wages must be increased to match market rates for unskilled labour.

Only 2.3 billion person-days of labour were generated both in 2015-16 and 2012-13, despite a 27 percent wage increase. (Photo: Reuters)

Why MGNREGA Needs a Rethink

After 10 years, it is clear that MGNREGA has not met most of its goals.

Poor participation shows that work is either not provided or demanded. Rural productivity remains poor, which raises questions about the quality of assets built with MGNREGA funds. Even the most vocal supporters of MGNREGA agree that the project has failed to produce durable assets and is mired in corruption.

This centrally-sponsored mega scheme could definitely be better targetted – at India’s poorest districts, where demand for work is high or limited to off-season periods.

Keeping with the spirit of cooperative federalism, the money could be given to the states directly to spend on schemes that work for them.

Either way, the government needs to seriously rethink its commitment to MGNREGA.

(This article has been published in collaboration with IndiaSpend. Shobhit Mathur, an IIT-B alumnus and MBA from the Indian School of Business, is the Executive Director, Vision India Foundation, which focuses on policy research, training and engagement of young talent in public policy and governance. Nomesh Bolia is an IIT-B alumnus and an associate professor at IIT Delhi. His research focuses on data- driven governance.)

(At The Quint, we question everything. Play an active role in shaping our journalism by becoming a member today.)

Published: 29 Apr 2016,01:22 PM IST