Over 7,000 Unmanned Rail Crossings Still Await Elimination

The government hopes to eliminate UMLCs by 2020. Gujarat has the most number of such unmanned level crossings.    

Rakesh Dubbudu
India
Published:
Image used for representational purpose.
i
Image used for representational purpose.
(Photo: Reuters)

advertisement

After a deadly accident killed 26 school children at an unmanned level crossing (UMLC) in Telangana in 2014, a PIL was filed in the Supreme Court (SC). The case went on for about one and a half years and the SC disposed it in 2016 after having convinced itself with the action plan submitted by the government. The government had submitted an affidavit to the SC in September 2015 with an action plan to eliminate UMLCs by 2020.

As it stands, more than 7000 UMLCs are still waiting to be eliminated as of 1 April 2017.

Close to Half the Level Crossings Are Unmanned in Western Railways

Out of the 29487 level crossings across India, 7701 or 26 percent are still unmanned as of 1 April 2017. Of the 7701, 4943 are on Broad Gauge, 1524 on Meter Gauge and 1234 on Narrow Gauge. Among the zones, 48 percent of the level crossings are still unmanned in Western Railways. Western Railways with 1907 also has the highest number of UMLCs. More than 30 percent of the level crossings are unmanned in four different zones and more than 20 percent in 10 zones.

Only the West Central Railway & Eastern Railway zones have eliminated virtually every UMLC. The Central Railway zone also eliminated all UMLCs on the broad gauge. The UMLCs in Central Railway zone are all on the narrow gauge.

Gujarat Has the Most Number of UMLCs

Among the states, Gujarat has the highest number of UMLCs. Gujarat has 791 UMLCs on broad gauge and 1104 on meter/narrow gauge making a total of 1895 UMLCs.

In fact, the four states of Gujarat, Uttar Pradesh, Bihar & Rajasthan make up for 60 percent of all the UMLCs in the country. Kerala on the other hand has only 7 UMLCs. Fourteen (14) States/UTs have less than 50 UMLCs each.

ADVERTISEMENT
ADVERTISEMENT

Considerable Progress in the Last 5 Years

In the last five years, a total of 6169 UMLCs have been eliminated. Of these five years, the highest number of UMLCs ie, 1503 have been eliminated in 2016-17. On average, about 1,250 UMLCs have been eliminated each year starting 2012-13. More than 500 UMLCs each have been eliminated in these five years in six zones.

199 Accidents at UMLCs in 5 Years

A total of 199 accidents took place at UMLCs between 2012-13 and 2016-17. The number of such accidents has come down to 20 in 2016-17 from 53 in 2012-13. Four zones that have the greater percentage of UMLCs are also in the top five zones with most accidents at UMLCs. During the same period, 21 accidents took place at manned level crossings.

Target to Eliminate UMLCs on Broad Gauge by 2020

The Ministry of Railways told a parliamentary standing committee that the following methods will be used to eliminate the UMLCs:

  • Closure – Closing UMLCs having NIL/negligible traffic volume
  • Merger – Merger of UMLCs to nearby LCs/grade-separators by Construction of diversion road.
  • Provision of Subways/RUBs
  • Manning – UMLCs which cannot be eliminated by above methods will be progressively manned

The government also told the parliamentary standing committee that all 4943 UMLCs on broad gauge will be eliminated by 2020. The government also told the standing committee that UMLCs on meter gauge network will be gradually removed along with gauge conversion work. In narrow gauge, the government plans to remove some UMLCs while the others will be manned. It is also heartening to note that there has been a near 100 percent utilisation of the allocated funds for road safety works in the last few years.

(This article was first published on Factly and has been edited for length.)