Nileena and Cherian Zachariah’s home in Kallissery in central Kerala’s Chengannur taluk became a refuge for several neighbours affected by the devastating floods that swept Kerala in August 2018. It was also a hub for relief work.
“We were lucky that our home was not damaged,” said Cherian, who moved back to Kerala in 2014 from Kuwait where he had worked for 20 years.
But the flood waters had left Chengannur without electricity. It was the worst-affected division in the state with six of seven sections flooded. By 16 August 2018, its sub-station – an electricity distribution point – had been switched off.
The Zachariahs were struggling to tend to the needs of the dozens of volunteers who slept over at their home. “Not having power was the biggest problem, especially for cooking and the use of toilets,” said Neelina.
The disaster left 2.56 million homes statewide without electricity. How the Kerala State Electricity Board (KSEB) restored power in these homes under a fortnight by mobilising and deploying every human resource at hand, including retired KSEB staff, engineering students and private electricians, doing away with red tape and questions of hierarchy and communication could be a model for every disaster-stricken state grappling with a similar problem.
The KSEB called its plan Mission Reconnect.
“The situation was unprecedented,” NS Pillai, chairman and managing director (CMD) of KSEB, told IndiaSpend. “We had to ensure that requests for materials and personnel on ground were provided without the usual delays of following government procedure.”
In the first part of this series on how Kerala is rebuilding itself post-flood, we looked at the role of a poor women’s collective. In this second part, we tell you how KSEB, which suffered a loss of nearly Rs 850 crore during the floods, dealt with the crisis. The flood waters damaged nearly 16,158 distribution transformers, 50 sub-stations, 15 large and small hydel stations, according to the KSEB data we accessed.
IndiaSpend traversed four districts – Alappuzha, Pathanamthitta, Ernakulam, and Thiruvananthapuram – to understand how the KSEB pulled off its mission.
The KSEB set up a state-level task force (SLTF) at its headquarters in Thiruvananthapuram consisting of a 24x7 control room. “Our primary role was to ensure communication to and from district level officials was seamless,” said Suresh Kumar C, deputy chief engineer leading the SLTF.
The challenge was to make human resource and material available at all levels of its functioning – from the control room in the state capital to section offices – and also ensure coordination between different wings of the board and between the board and external agencies.
But what ensured the mission’s success was the doggedness with which workers and volunteers made sure that they reached distressed homes and submerged villages.
In the three days following 15 August 2018, he travelled to work in a milkman’s boat from his home around 5 km away. “Although my house wasn’t affected, I had to wade or swim till I could access transport,” he said. “For a few days we stayed in office to restore power in different parts of the sub-division.”
Shyam Kumar, an assistant executive engineer, is a part of the project management unit (PMU) in Haripad circle. With senior officers stranded at home or in relief camps, he and his colleagues had to coordinate the restoration of infrastructure and supply to 1,20,000 consumers in Haripad. “We assumed charge under the circumstances,” said Shyam Kumar.
In order to ensure efficient coordination and communication, the PMU decided that seven nodal officers would be in-charge of each section office and local electrical installations would not be activated without their knowledge. This ensured that there were no transmission issues once sub-stations were resumed and activated.
Teams of line staff, supervisors would patrol the 11-KV high transmission lines and inform nodal officers about their status and repair requirements. The officers would then communicate the information to the circle and the control room.
Volunteers from engineering colleges, retired KSEB staff and wiremen visited individual homes to check installations like meters and wiring. “Considering Onam was around the corner, we were expecting establishments to be shut,” said Kumar. “We ensured that electrical supplies, line materials, transformers and so on were moved here from other circles.”
The priority for restoration was given to hospitals, railway stations, water pumping station and the telephone department in Chengannur.
Laila NG, assistant executive engineer at the Chengannur sub-division office, could only join work by 22 August 2018. Her home was a shelter to more than 20 neighbours hit by floods.
Just before the floods, 11 line staff had been transferred to new locations. This meant that the new people who had joined had little knowledge of the area and the distribution network.
“During a meeting, we requested that overseers and line staff be temporarily moved back so that they could help complete the restoration works quickly,” she said. The orders were passed immediately by the board in Thiruvananthapuram.
In Alangand too, a flood-hit section of Ernakulam, line staff and supervisors were transferred back to ensure that their familiarity with the region would hasten restoration work.
In some areas of Chengannur and Alangad, electric poles and lines had fallen into water-logged fields and wires were sagging. A team of eight KSEB staff with experience in working in water-logged areas helped resurrect the installations and pulled up the wires.
Transformers which were not damaged were charged, their oil replaced, and fuse removed to restore transmission. Nearly 99 percent of the 16,158 affected transformers had been restored as of 3 September 2018, as per KSEB data.
“It was the effort of our own staff, volunteers that helped us restore power within few days despite our 33 KV substation tripping due to the flood,” said Anil Kumar, assistant engineer in Alangand section.
In homes where it was not possible to supply power immediately due to structural damage, simple connections were provided which included safety device to prevent shock, a power socket to use motors for cleaning or other purposes, and a bulb holder. Nearly 700 such devices were provided.
The Kerala Electrical Wiremen and Supervisors Association, a private association of electrical workers, were vital in ensuring that homes were safe for power restoration.
“A group of 3-4 people would check the wiring of close to 150 homes a day, ideally in the presence of the homeowner,” said Jose Daniel, a member of the association in Chengannur. These men were among the first to wade through the slush and mud to damaged homes, often working late into the night.
Low-lying areas like Kuttanad, which routinely experience flooding during rains, were even tougher pockets to restore power.
Barely a couple of metres away from the backwater, files and papers lie strewn outside KSEB’s Kainakary office in Kuttanad. With an average elevation of 1 metre above mean sea level, it has the lowest altitude in India.
Kuttanad is used to annual waterlogging during monsoons but this was unprecedented, said locals.
During the July 2018 flood that hit parts of Alappuzha, including Kainakary, the damage had not been severe, said Anandan NK, assistant engineer, electrical section in Kainakary. “Water rose a foot inside the office in July,” he said. “But in the August flood, water rose five-feet inside the office and the strong currents damaged installations.”
Six of the 98 transformers in Kuttanad submerged and many others affected. The substation was switched off for nearly four days.
Small motor boats with teams of line staff and contractors cut supply to homes due to the rising waters. “With almost all the inhabitants of the region having been evacuated, patrolling at night in pitch dark was tough and dangerous,” said Ashok Kumar, a contractor with KSEB for 24 years and a flood-affected resident of Kainakary. “The clearance between the boat and the electric line was so low that we could be on the boat and check the wires in some places.”
In the districts IndiaSpend visited, rescue teams new to the area used electric lines to identify roads and pathways.
Volunteers helped identify unsafe homes with damaged installation like meters or wiring. Wherever possible, they marked meters using stickers – red for damaged and green for undamaged – and created a checklist for reference. The entire 58-km stretch of 11 KV lines in Kuttanad, 86 percent of which is on paddy fields located a few metres below mean sea level, was restored in five days.
“Usually, the motor pumps are used in paddy fields to deal with monsoon water-logging but most of them were damaged,” said Anandan. The need for boats also slowed down the progress. “Even now, close to 200 homes that are situated in the water-logged parts do not have power.”
Pathanamthitta and Ernakulam experienced similar issues.
Nearly 120 state electricity board board staff from Andhra Pradesh arrived with their own equipment to join Mission Reconnect.
KSEB received more than 20,000 electricity meters and transformers from Telangana, Tamil Nadu and Karnataka. Since the board was implementing the Integrated Power Development Scheme and Deen Dayal Upadhyaya Gram Jyoti Yojana – central schemes to improve power distribution and supply – it had a stock of electrical poles, meters and transformers it could put to use in restoration work.
“We received around 125 transformers from Tamil Nadu Generation and Distribution Corporation,” Santosh K, executive engineer in Pathanamthitta, told IndiaSpend. “More than 220 transformers were submerged here, but we were able to either replace or fix them within five days it thanks to the availability of replacement.”
The infrastructure loss alone in the district was Rs 33 crore. The KSEB has decided to not collect electricity dues till 31 January 2019, to give people time to tide over the financial distress caused by the floods.
(This is the second of a three-part series. You can read the first part here. Paliath is an analyst with IndiaSpend. This piece was originally published in IndiaSpend and has been republished with permission.)
(At The Quint, we question everything. Play an active role in shaping our journalism by becoming a member today.)